SEWER PROJECT UPDATE AS OF 07/19/19

What We Accomplished in the Past Two Weeks

  • Directed the surveyor to provide data for 3 additional streets.

  • Followed up with the IEPA regarding the approval of the Greenview treatment process.

  • Followed up with the IEPA regarding the review of the antidegradation process.

  • Received initial WWTF preprocurement comments from the USDA state engineer.

  • Responded to the state engineer’s initial comments.

  • Received additional WWTF preprocurement comments from the USDA state engineer.

  • Developed over 30 sheets of sewer plans.

  • Completed the mechanical design of the pump station.

  • Issued letter requesting septic system surveys.

  • Planned “office hours” in the Village to address homeowner questions regarding the survey.

 

What We Will Accomplish in the Next Two Weeks

  • Review the preliminary layout of the collection system and pump station.

  • Incorporate internal review comments.

  • Update cost estimates.

  • Submit the preliminary collection system and pump station plans to the USDA state engineer.

    • Preliminary Plans

    • Outline Specifications

    • Revised Opinion of Probable Cost

  • Address USDA state engineer’s comments on the WWTF preprocurement.

  • Hold “office hours” at the Village to address citizen questions regarding the survey.

 

Scope Changes to Date

  • None

 

Schedule/Deliverable Status

  • On schedule.

  • Preliminary Design Phase (Due 10/11/2019)

    • Survey – expected 6/10

    • Geotechnical – expected 6/10

    • Preliminary Design submittal – expected 8/2

  • Final Design Phase (Due 6/2/2020)

  • Bidding or Negotiation Phase (Due 9/22/20)

  • Construction Phase (Estimated Completion 9/7/2021)

  • Post – Construction Phase (Estimated Completion 10/19/2021)