NOTE FROM THE VILLAGE PRESIDENT

As you all know our sewer system is underway and progressing quickly and will require a little information from you.    In the next few weeks residents will be receiving a letter requesting where your septic pipe exits your foundation.  It is VERY IMPORTANT that these get returned as quickly as possible as it helps with the design of the new Wastewater Treatment Facility.  If you do not have that information the engineers will be here a couple of days at the end of July to assist residents with this.  Please be on the lookout for the letter and if you have any questions please do not hesitate to call Village Hall at 217-968-5314.

Thank you

Kevin Curry

President

Village of Greenview



A-Team Disposal

A-Team Disposal was present at our board meeting on July 1, 2019 presenting that they are now offering waste hauling service in the Greenview area.

Their rates are $21.00 per month or $63 per quarter, with the use of one of their toters included.

Pick-up would be on Wednesdays, starting July 3, 2019

They informed the Village Board to be on the lookout for their Red containers, White trucks, and bright blue trash totes.

Any questions please call them at 217-501-4640

SEWER PROJECT UPDATE AS OF 06/21/19

Sewer Update as of 06/21/2019

 

What has been accomplished in the past 2 weeks:

·          Reviewed incomplete survey data.

o   Directed surveyor to provide additional data in accordance with the contract.

o   Surveyor collection additional points

·          Conducted internal review of WWTF procurement documents

·         Submitted WWTF procurement documents to USA for review

·         Conducted internal review of engineering report

·         Submitted engineering report to IEPA for review

·         Began preliminary layout of collection system

 

What will be accomplished in the next two weeks:

 

·          Continue preliminary layout of collection system

·         Begin preliminary layout of influent lift station

·         Begin septic system surveys

·         Receive completed base mapping

Schedule Status

·          On schedule

·         Preliminary design phase (due 10/11/19)

·         Preliminary design submittal – expected 08/02/19

·         Final design phase – due 06/02/20

·         Bidding or Negotiation Phase due 09/22/20

·         Construction Phase – estimated completion 09/07/2021

·         Post-Construction Phase – estimated completion 10/19/2021

SEWER PROJECT UPDATE AS OF 06/07/19

What’s been accomplished so far:

  • Geotechnical submitted report

  • Finalized permit and discharge requirements

  • Submitted discharge permit to internal review

  • Completed permit plans and illustrations

What will be accomplished in the next two weeks:

  • Receive completed base mapping

  • Initiate collection system design

  • Submit precontract procurement package to State Engineer for review

  • Plan to submit discharge permit request to the EPA

Schedule Status

  • On schedule

  • Preliminary Design Phase - Due 10/11/19

  • Final Design Phase - Due 06/02/20

  • Bidding or Negotiation Phase - Due 09/22/20

  • Construction Phase - Estimated completion 09/07/21

  • Post-Construction Phase - Estimated completion 10/19/21

PUBLIC HEARING 05/06/19

Notice of Public Hearing

 The Village of Greenview will be holding a public hearing on 05/06/2019 at 6:00 pm at 106 E Washington Street, Greenview, IL.                   

For Angela Dowell obtaining a special use permit for a temporary building to be placed on the vacant lot on the corner of Washington and North Engle street planning on opening an ice cream shop.