SEWER PROJECT UPDATE AS OF 06/07/19

What’s been accomplished so far:

  • Geotechnical submitted report

  • Finalized permit and discharge requirements

  • Submitted discharge permit to internal review

  • Completed permit plans and illustrations

What will be accomplished in the next two weeks:

  • Receive completed base mapping

  • Initiate collection system design

  • Submit precontract procurement package to State Engineer for review

  • Plan to submit discharge permit request to the EPA

Schedule Status

  • On schedule

  • Preliminary Design Phase - Due 10/11/19

  • Final Design Phase - Due 06/02/20

  • Bidding or Negotiation Phase - Due 09/22/20

  • Construction Phase - Estimated completion 09/07/21

  • Post-Construction Phase - Estimated completion 10/19/21