SEWER PROJECT UPDATE AS OF 02/15/19

In the past 2 weeks the surveyors have been onsite and kickoff notes to the Geotech firm have been issued.  In the next two weeks expect the surveying work to continue and communication with the geotechnical firm as to a start date.

 

Schedule Status – On schedule

Preliminary Design Phase (Due 10/11/19)

·          Survey – expected 04/26/19

·         Geotechnical – expected 03/15/19

·         Preliminary Design submittal – expected 08/02/19