SEWER PROJECT UPDATE

We apologize for the delay in the update for the sewer project. Below is a timeline of the entire project and we will have bi-weekly updates posted.

Preliminary Design Phase

·          Survey – 8 weeks – 01/07/19 – 03/01/19

·         Geotechnical – 6 weeks- 01/07/19-02/15/19

·         Preliminary Design – 150 days- 01/07/19-08/02/19

·         Board Review – 4 weeks -08/05/19-08/30/19

·         Preliminary Revisions – 30 day -09/02/19-10/11/19

Final Design Phase

·          Final Design – 90 days – 10/14/19-02/14/20

·         Board Review – 4 weeks – 02/17/20-03/13/20

·         Final Revisions – 60 days – 03/16/20-06/05/20

Bidding/Negotiating Phase

·          Advertise for Bids – 30 days – 07/01/20-08/11/20

·         Bid Opening – 0 days – 08/11/20

·         Bid Award – 30 days 08/12/20-09/22/20

Construction Phase

·          Contract Execution – 2 weeks – 09/23/20-10/06/20

·         Notice to Proceed – 0 days – 10/06/20

·         Construction – 12 months – 10/07/20-09/07/21

Post Construction Phase

·          Record Drawings – 30 days – 09/08/21-10/19/21

·         Operations & Maintenance Manual – 30 days – 09/08/21-10/19/21