SEWER PROJECT UPDATE AS OF 02/15/19

In the past 2 weeks the surveyors have been onsite and kickoff notes to the Geotech firm have been issued.  In the next two weeks expect the surveying work to continue and communication with the geotechnical firm as to a start date.

 

Schedule Status – On schedule

Preliminary Design Phase (Due 10/11/19)

·          Survey – expected 04/26/19

·         Geotechnical – expected 03/15/19

·         Preliminary Design submittal – expected 08/02/19

SEWER PROJECT UPDATE

We apologize for the delay in the update for the sewer project. Below is a timeline of the entire project and we will have bi-weekly updates posted.

Preliminary Design Phase

·          Survey – 8 weeks – 01/07/19 – 03/01/19

·         Geotechnical – 6 weeks- 01/07/19-02/15/19

·         Preliminary Design – 150 days- 01/07/19-08/02/19

·         Board Review – 4 weeks -08/05/19-08/30/19

·         Preliminary Revisions – 30 day -09/02/19-10/11/19

Final Design Phase

·          Final Design – 90 days – 10/14/19-02/14/20

·         Board Review – 4 weeks – 02/17/20-03/13/20

·         Final Revisions – 60 days – 03/16/20-06/05/20

Bidding/Negotiating Phase

·          Advertise for Bids – 30 days – 07/01/20-08/11/20

·         Bid Opening – 0 days – 08/11/20

·         Bid Award – 30 days 08/12/20-09/22/20

Construction Phase

·          Contract Execution – 2 weeks – 09/23/20-10/06/20

·         Notice to Proceed – 0 days – 10/06/20

·         Construction – 12 months – 10/07/20-09/07/21

Post Construction Phase

·          Record Drawings – 30 days – 09/08/21-10/19/21

·         Operations & Maintenance Manual – 30 days – 09/08/21-10/19/21

VILLAGE PRESIDENT HORN RESIGNS AND NEW PRESIDENT NAMES

The Village of Greenview Board of Trustees voted to accept President Daniel Horn’s resignation effective 12/17/18.  The Board would like to thank Dan for his many years of service and dedication to our community.  He will be missed.

We are pleased to announce that the board voted to approve Kevin Curry as the new President. 

Mr. Curry has many years of on the Village Board as a Trustee and will bring a great deal of experience to the position. 

If anyone has any questions please feel free to contact Village Hall at 217-968-5314

  • Our Village Website will be updated in April

Paint Night

Picasso on the Prairie is helping put on a fundraising paint night for the Greenview Community Park Committee. On January 25, 2019 we will be at the greenview amvets building. Doors open roughly 6:00pm and we will start painting at 6:30pm. Cost is $40 per painter. Sign up online at picasso on the prairie website. Payment will be due at the door. https://m.facebook.com/picassoontheprairie/
From the facebook profile, click on the website then sign up. You will then find the river scene and be able to sign up for the event. Thank you!!

picasso on the prairie.jpg